The development includes: a new unmanned conductor platform (CP2), a new gathering station platform (PT1), a new drilling platform (ODB) bridge‑linked to the existing ODA platform, a new processing platform (OPB) bridge‑linked to the existing OPA platform, brownfield modifications to OPA and ODA platforms and two new pipelines.
ROC engaged MaisonWorleyParsons to carry out detailed design and procurement activities for the expansion. Our specialist centers performed the FEED phase, with the PT1 and CP2 FEEDs performed in Melbourne, ODB and OPB, and brownfield FEEDs performed in New Plymouth, pipelines FEED and detailed design performed in Singapore, and the detailed design for the brownfield modifications and the four new platforms with full procurement services performed in Beijing.
The successful use of extensive workshare for this project, with the majority of the hours being executed in Beijing, provided ROC with access to lower base cost specialist input and the ability to be local to the Chinese fabrication and installation areas for construction and commissioning support.