Worley Trinidad awarded FEED for production facility

 01-July-2004
Figure
Worley Trinidad has been awarded Front End Engineering and Design (FEED) for BG Trinidad Central Block's Production Facility.

Central Block is a 111 square kilometer onshore gas field located in south Trinidad.

This award was single sourced and follows Worley's successful completion of the concept design for Central Block Production Facility and FEED for ECMA Beachfield Onshore Facilities, also for BG T&T.

The FEED work will commence on 25 June 2004, and is planned for completion within 14 weeks.